Start from the need, not the supplier
Good purchasing starts inside the company. A Material Request records that a warehouse, a production order or a department needs something, before anyone calls a supplier. ERPNext can raise material requests automatically when stock falls below the reorder level.
The chain, step by step
The standard buying flow follows the same idea as selling: each document comes from the one before it.
- 1.Material Request: what is needed, how much and by when.
- 2.Request for Quotation: the same need sent to several suppliers at once.
- 3.Supplier Quotation: each supplier's prices and terms, recorded so you can compare them side by side.
- 4.Purchase Order: the commitment to one supplier, with agreed prices and delivery dates.
- 5.Purchase Receipt: the goods arrive in the warehouse and stock is updated at their value.
- 6.Purchase Invoice: the supplier's bill is matched to the order and receipt, and the payable is posted.
- 7.Payment Entry: the supplier is paid and the invoice is closed.
Shipping costs and returns
Freight, customs and clearance change the real cost of what you bought. A Landed Cost Voucher spreads those charges over the received items, so stock valuation and later margins are correct.
When goods go back to a supplier, create the return from the original Purchase Receipt or Purchase Invoice. The debit note then references the original purchase and reverses stock and accounts cleanly.
Reports to watch
Accounts Payable shows what you owe and when it falls due. Purchase Analytics shows spend by supplier and item. The purchase order analysis shows what was ordered but not yet received or billed, which is where delays hide.